Pontiac Midpoint II 345kV (U4-012)

Pontiac Midpoint II 345kV is a 200.0 MW wind interconnection project in McLean, Illinois with a current status of withdrawn.

200.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical namePontiac Midpoint II 345kV
Queue IDU4-012
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity200.0 MW
StateIllinois
CountyMcLean
Point of interconnection
Requested (queue) date2008-11-20
Proposed in-service date2011-12-31
Operational date
Withdrawn date2012-11-27
Developer
Utility / transmission ownerComEd

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata