Post Rock - Spearville 345 kV is a 250.0 MW wind interconnection project in Edwards/Hodgeman, Kansas with a current status of withdrawn. It is proposed to connect at Post Rock - Spearville 345 kV.

250.0 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology

Project facts

Canonical namePost Rock - Spearville 345 kV
Queue IDGEN-2022-205
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyWind
Capacity250.0 MW
StateKansas
CountyEdwards/Hodgeman
Point of interconnectionPost Rock - Spearville 345 kV
Requested (queue) date2023-03-01
Proposed in-service date2027-11-01
Operational date
Withdrawn date2025-03-06
Developer
Utility / transmission ownerITCGP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata