ITCGP — Interconnection Queue Projects
ITCGP is associated with 43 tracked interconnection projects representing 8,897 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
43Projects
11Active
4Operational
28Withdrawn
8,897 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 26 | 5,722 MW |
| Solar | 10 | 1,952 MW |
| Battery | 6 | 866 MW |
| Gas | 1 | 357 MW |
Geographic footprint
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Cirrus 345 kV Substation | GEN-2024-067 | Solar | 380.0 MW | operational | Cloud, Kansas |
| ITC Hugo 7 345 kV Substation | GEN-2024-323 | Gas | 356.8 MW | operational | Choctaw, Oklahoma |
| Clark County - Thistle 345 kV line break | GEN-2022-192 | Wind | 300.0 MW | withdrawn | Ford, Kansas |
| Elm Creek 345 kV Substation | GEN-2024-215 | Solar | 300.0 MW | operational | Aurora, Kansas |
| Post Rock - Macon 345 kV Line | GEN-2024-016 | Wind | 300.0 MW | withdrawn | Smith, Kansas |
| Postrock to Axtell 345 KV line | GEN-2020-070 | Wind | 255.0 MW | withdrawn | Osborne, Kansas |
| Spearville to Clark County 345 kV line | GEN-2019-030 | Wind | 252.0 MW | active | Ford, Kansas |
| Spearville to Clark County 345 kV line | GEN-2026-SR9 | Battery | 252.0 MW | active | Wright, Kansas |
| Hugo 345 kV Substation | GEN-2024-083 | Solar | 250.0 MW | withdrawn | Choctaw, Oklahoma |
| Post Rock - Axtell3 345 kV line | GEN-2023-139 | Wind | 250.0 MW | withdrawn | Osborne And Rooks, Kansas |
| Post Rock - Spearville 345 kV | GEN-2022-205 | Wind | 250.0 MW | withdrawn | Edwards/Hodgeman, Kansas |
| Post Rock - Spearville 345 kV Line | GEN-2024-196 | Wind | 250.0 MW | withdrawn | Kinsley, Kansas |
| Post Rock - Spearville 345 kV | GEN-2022-204 | Wind | 250.0 MW | withdrawn | Edwards/Hodgeman, Kansas |
| Post Rock - Spearville 345 kV | GEN-2022-206 | Wind | 250.0 MW | withdrawn | Edwards/Hodgeman, Kansas |
| Post Rock - Spearville 345 kV Line | GEN-2024-195 | Wind | 250.0 MW | withdrawn | Kinsley, Kansas |
| Postrock to Axtell 345 kV line | GEN-2022-095 | Wind | 250.0 MW | withdrawn | Osborne, Kansas |
| Postrock to Axtell 345 kV line | GEN-2022-094 | Wind | 250.0 MW | withdrawn | Osborne, Kansas |
| Post Rock - Spearville 345 kV Line | GEN-2024-197 | Wind | 250.0 MW | withdrawn | Kinsley, Kansas |
| Post Rock - Axtell3 345 kV line | GEN-2023-140 | Wind | 250.0 MW | withdrawn | Osborne And Rooks, Kansas |
| Postrock to Axtell 345 kV line | GEN-2022-096 | Wind | 225.0 MW | withdrawn | Osborne, Kansas |
| Post Rock - Axtell3 345 kV line | GEN-2023-141 | Wind | 225.0 MW | withdrawn | Osborne And Rooks, Kansas |
| Post Rock - Spearville 345 kV | GEN-2017-063 | Wind | 202.1 MW | withdrawn | Rush County, Kansas |
| Elm Creek - Summit 345 kV | GEN-2017-004 | Wind | 201.6 MW | active | Cloud County, Kansas |
| Clark County - Thistle 345 kV line break | GEN-2022-194 | Wind | 200.0 MW | withdrawn | Kiowa, Kansas |
| Post Rock - Spearville 345 kV | GEN-2017-021 | Wind | 200.0 MW | withdrawn | Edwards County, Kansas |
| Clark County - Thistle 345 kV line break | GEN-2022-193 | Wind | 200.0 MW | withdrawn | Ford, Kansas |
| Spearville - Postrock 345kV Substation | GEN-2022-158 | Solar | 200.0 MW | withdrawn | Rush, Kansas |
| Clark County - Thistle 345 kV line break | GEN-2022-190 | Wind | 200.0 MW | withdrawn | Kiowa, Kansas |
| ITC Great Plains Saddle 345 kV Substation | GEN-2024-189 | Battery | 199.0 MW | withdrawn | Ford, Kansas |
| Thistle 345 kV sub | GEN-2017-018 | Solar | 189.0 MW | active | Barber County, Kansas |
| Elm Creek 345kV substation | GEN-2017-119 | Wind | 180.0 MW | withdrawn | Cloud/Mitchell, Kansas |
| Tap on the Spearville - Post Rock 345kV line | GEN-2022-075 | Solar | 175.0 MW | active | Ellis, Kansas |
| Post Rock - Spearville 345 kV | GEN-2017-099 | Wind | 150.0 MW | withdrawn | Edwards County, Kansas |
| Clark County 345kV substation | GEN-2019-058 | Solar | 150.0 MW | active | Ford, Clark, Kansas |
| Clark County 345kV Substation | GEN-2025-SR3 | Battery | 150.0 MW | active | Minneola, Kansas |
| Thistle 345kV Substation | GEN-2026-SR24 | Battery | 120.0 MW | active | Barber, Kansas |
| Thistle 345kV Substation | GEN-2018-049 | Solar | 120.0 MW | active | Sumner, Kansas |
| ITC Post Rock 345 kV Substation | GEN-2021-076 | Solar | 113.0 MW | withdrawn | Ellis, Kansas |
| Thistle 345kV substation | GEN-2018-108 | Battery | 95.0 MW | active | Barber, Kansas |
| Flat Ridge Tap 138kV | GEN-2006-021 | Wind | 94.0 MW | operational | Barber County, Kansas |
| Elm Creek 345 kV interconnection substation | GEN-2021-011 | Solar | 74.9 MW | withdrawn | Cloud And Mitchell, Kansas |
| Clark County 345kV substation | GEN-2019-063 | Battery | 50.0 MW | active | Ford, Clark, Kansas |
| Elm Creek 345 kV interconnection substation | GEN-2021-017 | Wind | 37.5 MW | withdrawn | Cloud And Mitchell, Kansas |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through ITCGP.