Powerton-Nevada 345 kV (AD2-038)

Powerton-Nevada 345 kV is a 150.0 MW wind interconnection project in Lasalle, Illinois with a current status of operational.

150.0 MWCapacity
OperationalStatus
—Market
WindTechnology

Project facts

Canonical namePowerton-Nevada 345 kV
Queue IDAD2-038
Statusoperational
Source statusPartially in Service - Under Construction
Market—
TechnologyWind
Capacity150.0 MW
StateIllinois
CountyLasalle
Point of interconnection—
Requested (queue) date2018-01-22
Proposed in-service date—
Operational date2026-10-30
Withdrawn date—
Developer—
Utility / transmission ownerComEd

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-26statusactiveoperationalhigh
2026-08-26proposed_online_date2026-10-30—medium
2026-08-26operational_date—2026-10-30medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata