Praire - Winger (J2285)

Praire - Winger is a 45.0 MW battery interconnection project in Polk, Minnesota with a current status of withdrawn. It is proposed to connect at Praire - Winger.

45.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical namePraire - Winger
Queue IDJ2285
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity45.0 MW
StateMinnesota
CountyPolk
Point of interconnectionPraire - Winger
Requested (queue) date2021-07-14
Proposed in-service date2026-10-01
Operational date2026-10-01
Withdrawn date2021-09-10
Developer
Utility / transmission ownerOtter Tail Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.