Project Pivot and Specialized is a 484.0 MW other interconnection project in Umatilla, Oregon with a current status of active. It is proposed to connect at McNary Substation.

484.0 MWCapacity
ActiveStatus
ORMarket
OtherTechnology

Project facts

Canonical nameProject Pivot and Specialized
Queue IDL0499
Statusactive
Source statusSTUDY
MarketOR
TechnologyOther
Capacity484.0 MW
StateOregon
CountyUmatilla
Point of interconnectionMcNary Substation
Requested (queue) date2021-08-13
Proposed in-service date2024-08-09
Operational date
Withdrawn date
DeveloperPacifiCorp
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata