Proving Ground BESS (26INR0159)

Proving Ground BESS is a 51.4 MW other interconnection project in Schleicher, Texas with a current status of operational. It is proposed to connect at Tap 138kV 6500 Live Oak - 6490 Santiago .

51.4 MWCapacity
OperationalStatus
SchleicherMarket
OtherTechnology

Project facts

Canonical nameProving Ground BESS
Queue ID26INR0159
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketSchleicher
TechnologyOther
Capacity51.4 MW
StateTexas
CountySchleicher
Point of interconnectionTap 138kV 6500 Live Oak - 6490 Santiago
Requested (queue) date2023-07-10
Proposed in-service date
Operational date2028-06-30
Withdrawn date
DeveloperLantana Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata