PSEG Bridgeport Harbor CCGT Expansion (412)

PSEG Bridgeport Harbor CCGT Expansion is a 509.6 MW gas interconnection project in Fairfield, Connecticut with a current status of operational. It is proposed to connect at UI 345 kV Singer.

509.6 MWCapacity
OperationalStatus
SWCTMarket
GasTechnology

Project facts

Canonical namePSEG Bridgeport Harbor CCGT Expansion
Queue ID412
Statusoperational
Source statusC
MarketSWCT
TechnologyGas
Capacity509.6 MW
StateConnecticut
CountyFairfield
Point of interconnectionUI 345 kV Singer
Requested (queue) date2013-02-28
Proposed in-service date
Operational date2019-06-10
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata