QMB2 Storage II (1570)

QMB2 Storage II is a 200.0 MW battery interconnection project in Queens, New York with a current status of withdrawn. It is proposed to connect at Corona 138kV station.

200.0 MWCapacity
WithdrawnStatus
JMarket
BatteryTechnology

Project facts

Canonical nameQMB2 Storage II
Queue ID1570
Statuswithdrawn
Source status0
MarketJ
TechnologyBattery
Capacity200.0 MW
StateNew York
CountyQueens
Point of interconnectionCorona 138kV station
Requested (queue) date2023-06-20
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperQMB 2 Energy Storage, LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.