Radar Hill Substation (L0421)
Radar Hill Substation is a 40.0 MW other interconnection project in Walla Walla, Washington with a current status of operational. It is proposed to connect at Scooteney Tap-Midway-Benton #1 115 kV.
40.0 MWCapacity
OperationalStatus
WAMarket
OtherTechnology
Project facts
| Canonical name | Radar Hill Substation |
|---|---|
| Queue ID | L0421 |
| Status | operational |
| Source status | ENERGIZED |
| Market | WA |
| Technology | Other |
| Capacity | 40.0 MW |
| State | Washington |
| County | Walla Walla |
| Point of interconnection | Scooteney Tap-Midway-Benton #1 115 kV |
| Requested (queue) date | 2017-11-07 |
| Proposed in-service date | — |
| Operational date | 2020-11-07 |
| Withdrawn date | — |
| Developer | Big Bend Electric Cooperative, Inc. |
| Utility / transmission owner | Bonneville Power Administration |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.