Rawhide Prairie Solar Hybrid (63722_PV1)

Rawhide Prairie Solar Hybrid is a 22.0 MW solar interconnection project in Larimer, Colorado with a current status of operational.

22.0 MWCapacity
OperationalStatus
PSCOMarket
SolarTechnology

Project facts

Canonical nameRawhide Prairie Solar Hybrid
Queue ID63722_PV1
Statusoperational
Source status(OP) Operating
MarketPSCO
TechnologySolar
Capacity22.0 MW
StateColorado
CountyLarimer
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2021-03-01
Withdrawn date—
Developer—
Utility / transmission ownerGreenbacker Renewable Energy Corporation

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.