RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) (28INR0108)
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) is a 570.0 MW gas interconnection project in Grayson, Texas with a current status of operational. It is proposed to connect at Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch.
570.0 MWCapacity
OperationalStatus
GraysonMarket
GasTechnology
Project facts
| Canonical name | RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) |
|---|---|
| Queue ID | 28INR0108 |
| Status | operational |
| Source status | SS Completed, FIS Started, IA |
| Market | Grayson |
| Technology | Gas |
| Capacity | 570.0 MW |
| State | Texas |
| County | Grayson |
| Point of interconnection | Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch |
| Requested (queue) date | 2025-01-13 |
| Proposed in-service date | — |
| Operational date | 2028-02-26 |
| Withdrawn date | — |
| Developer | Rayburn Country Electric Cooperative, Inc. |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata