Reid EHV (J3089)

Reid EHV is a 696.0 MW gas interconnection project in Webster, Kentucky with a current status of withdrawn. It is proposed to connect at Reid EHV.

696.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameReid EHV
Queue IDJ3089
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity696.0 MW
StateKentucky
CountyWebster
Point of interconnectionReid EHV
Requested (queue) date2022-09-15
Proposed in-service date2029-04-30
Operational date2029-04-30
Withdrawn date2025-10-27
Developer
Utility / transmission ownerBIG RIVERS ELECTRIC CORPORATION

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.