Reis Solar (25INR0082)
Reis Solar is a 105.5 MW solar interconnection project in Atascosa, Texas with a current status of operational. It is proposed to connect at Tapping into 138 kV line (5689) Choke Canyon AEP to (5902) San Miguel Gen.
105.5 MWCapacity
OperationalStatus
AtascosaMarket
SolarTechnology
Project facts
| Canonical name | Reis Solar |
|---|---|
| Queue ID | 25INR0082 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Atascosa |
| Technology | Solar |
| Capacity | 105.5 MW |
| State | Texas |
| County | Atascosa |
| Point of interconnection | Tapping into 138 kV line (5689) Choke Canyon AEP to (5902) San Miguel Gen |
| Requested (queue) date | 2022-06-02 |
| Proposed in-service date | — |
| Operational date | 2027-08-03 |
| Withdrawn date | — |
| Developer | Greenalia Solar Power Reis LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.