Reno - Summit 345kV (GEN-2016-114)

Reno - Summit 345kV is a 310.0 MW wind interconnection project in McPherson, Kansas with a current status of withdrawn. It is proposed to connect at Reno - Summit 345kV.

310.0 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology

Project facts

Canonical nameReno - Summit 345kV
Queue IDGEN-2016-114
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyWind
Capacity310.0 MW
StateKansas
CountyMcPherson
Point of interconnectionReno - Summit 345kV
Requested (queue) date2020-10-02
Proposed in-service date2020-12-31
Operational date
Withdrawn date2021-03-16
Developer
Utility / transmission ownerWERE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata