Rio Vista Solar is a 553.7 MW solar interconnection project in Pecos, Texas with a current status of operational. It is proposed to connect at Tap 138kV #60393 PigCreek4A – #60385 Solstice4A.

553.7 MWCapacity
OperationalStatus
PecosMarket
SolarTechnology

Project facts

Canonical nameRio Vista Solar
Queue ID28INR0260
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketPecos
TechnologySolar
Capacity553.7 MW
StateTexas
CountyPecos
Point of interconnectionTap 138kV #60393 PigCreek4A – #60385 Solstice4A
Requested (queue) date2025-06-19
Proposed in-service date
Operational date2028-10-16
Withdrawn date
DeveloperRio Vista Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.