Riptide Storage (C26-0025)

Riptide Storage is a 200.0 MW battery interconnection project in Suffolk, New York with a current status of active. It is proposed to connect at POI is Edwards Avenue 138 kV Substation via existing position for Riverhead Solar Farm/Q535 Riverhead Solar 2 Projects.

200.0 MWCapacity
ActiveStatus
KMarket
BatteryTechnology

Project facts

Canonical nameRiptide Storage
Queue IDC26-0025
Statusactive
Source status1
MarketK
TechnologyBattery
Capacity200.0 MW
StateNew York
CountySuffolk
Point of interconnectionPOI is Edwards Avenue 138 kV Substation via existing position for Riverhead Solar Farm/Q535 Riverhead Solar 2 Projects
Requested (queue) date2026-08-14
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperACE DEVCO NC, LLC
Utility / transmission ownerLIPA

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-12new_project—activehigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.