Riverbank Energy is a 200.0 MW battery interconnection project in Cook, Illinois with a current status of active. It is proposed to connect at Burnham 138kV.

200.0 MWCapacity
ActiveStatus
PJMMarket
BatteryTechnology

Project facts

Canonical nameRiverbank Energy
Queue IDAF2-441
Statusactive
Source statusactive
MarketPJM
TechnologyBattery
Capacity200.0 MW
StateIllinois
CountyCook
Point of interconnectionBurnham 138kV
Requested (queue) date2020-03-31
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperLincoln Reserve Energy, LLC
Utility / transmission ownerComEd

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata