RMLD DER Group Study is a 10.0 MW battery interconnection project in Middlesex, Massachusetts with a current status of withdrawn. It is proposed to connect at RMLD Station 3/NG S145 & T146 Lines.

10.0 MWCapacity
WithdrawnStatus
CMAMarket
BatteryTechnology

Project facts

Canonical nameRMLD DER Group Study
Queue ID1580
Statuswithdrawn
Source statusW
MarketCMA
TechnologyBattery
Capacity10.0 MW
StateMassachusetts
CountyMiddlesex
Point of interconnectionRMLD Station 3/NG S145 & T146 Lines
Requested (queue) date2024-07-29
Proposed in-service date2025-06-16
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.