Rocking X Solar is a 602.2 MW solar interconnection project in Parker, Texas with a current status of operational. It is proposed to connect at Tap the 345 kV Parker Switch (bus#1436) – Comanche Peak SES (bus#1900) Double-Circuit line, Circuit 1..
602.2 MWCapacity
OperationalStatus
ParkerMarket
SolarTechnology
Project facts
| Canonical name | Rocking X Solar |
|---|---|
| Queue ID | 23INR0368 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Parker |
| Technology | Solar |
| Capacity | 602.2 MW |
| State | Texas |
| County | Parker |
| Point of interconnection | Tap the 345 kV Parker Switch (bus#1436) – Comanche Peak SES (bus#1900) Double-Circuit line, Circuit 1. |
| Requested (queue) date | 2023-10-04 |
| Proposed in-service date | — |
| Operational date | 2027-09-20 |
| Withdrawn date | — |
| Developer | 7100 Tin Top LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.