Rocky Road (AE2-312)

Rocky Road is a 7.0 MW gas interconnection project in Kane, Illinois with a current status of withdrawn.

7.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameRocky Road
Queue IDAE2-312
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity7.0 MW
StateIllinois
CountyKane
Point of interconnection
Requested (queue) date2019-03-29
Proposed in-service date2019-06-01
Operational date
Withdrawn date2019-04-04
Developer
Utility / transmission ownerComEd

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.