Roseland Solar (20INR0205)

Roseland Solar is a 254.0 MW solar interconnection project in Falls, Texas with a current status of operational. It is proposed to connect at tap 345kV 3390 Jewett - 3399 Ratsnake.

254.0 MWCapacity
OperationalStatus
FallsMarket
SolarTechnology

Project facts

Canonical nameRoseland Solar
Queue ID20INR0205
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketFalls
TechnologySolar
Capacity254.0 MW
StateTexas
CountyFalls
Point of interconnectiontap 345kV 3390 Jewett - 3399 Ratsnake
Requested (queue) date2018-11-30
Proposed in-service date
Operational date2025-11-29
Withdrawn date
DeveloperEnel X
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.