Russet Ridge Wind (1417)

Russet Ridge Wind is a 118.0 MW wind interconnection project in Livingston, New York with a current status of withdrawn. It is proposed to connect at Eelpot Road 115kV substation.

118.0 MWCapacity
WithdrawnStatus
CMarket
WindTechnology

Project facts

Canonical nameRusset Ridge Wind
Queue ID1417
Statuswithdrawn
Source status0
MarketC
TechnologyWind
Capacity118.0 MW
StateNew York
CountyLivingston
Point of interconnectionEelpot Road 115kV substation
Requested (queue) date2022-08-19
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperLiberty Renewables Inc.
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata