RV Solar (GI-136)

RV Solar is a 100.0 MW solar interconnection project in Tattnall County, Georgia with a current status of active. It is proposed to connect at Claxton-Ludowici Primary 115 kV.

100.0 MWCapacity
ActiveStatus
GAMarket
SolarTechnology

Project facts

Canonical nameRV Solar
Queue IDGI-136
Statusactive
Source statusFacilities Study
MarketGA
TechnologySolar
Capacity100.0 MW
StateGeorgia
CountyTattnall County
Point of interconnectionClaxton-Ludowici Primary 115 kV
Requested (queue) date2020-02-23
Proposed in-service date2022-09-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: gtc-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata