S1263 Brock 161kV substation (GEN-2019-009)
S1263 Brock 161kV substation is a 100.0 MW solar interconnection project in Nemaha, Nebraska with a current status of withdrawn. It is proposed to connect at S1263 Brock 161kV substation.
100.0 MWCapacity
WithdrawnStatus
NEMarket
SolarTechnology
Project facts
| Canonical name | S1263 Brock 161kV substation |
|---|---|
| Queue ID | GEN-2019-009 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | NE |
| Technology | Solar |
| Capacity | 100.0 MW |
| State | Nebraska |
| County | Nemaha |
| Point of interconnection | S1263 Brock 161kV substation |
| Requested (queue) date | 2019-04-24 |
| Proposed in-service date | 2029-11-01 |
| Operational date | — |
| Withdrawn date | 2026-03-23 |
| Developer | — |
| Utility / transmission owner | OPPD |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata