Salt City Solar Project - Hybrid (65302_BESS)
Salt City Solar Project - Hybrid is a 12.5 MW battery interconnection project in Ross, Ohio with a current status of active.
12.5 MWCapacity
ActiveStatus
PJMMarket
BatteryTechnology
Project facts
| Canonical name | Salt City Solar Project - Hybrid |
|---|---|
| Queue ID | 65302_BESS |
| Status | active |
| Source status | (P) Planned for installation, but regulatory approvals not initiated |
| Market | PJM |
| Technology | Battery |
| Capacity | 12.5 MW |
| State | Ohio |
| County | Ross |
| Point of interconnection | — |
| Requested (queue) date | — |
| Proposed in-service date | 2027-06-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Salt City Solar LLC |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-02 | new_project | — | active | high |
Explore related data
Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-28
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.