Samson Solar 3 (21INR0491)

Samson Solar 3 is a 250.0 MW solar interconnection project in Lamar, Texas with a current status of operational. It is proposed to connect at tap both 345kV 1685 FarmersVl - 1695 Moses ckts.

250.0 MWCapacity
OperationalStatus
LamarMarket
SolarTechnology

Project facts

Canonical nameSamson Solar 3
Queue ID21INR0491
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketLamar
TechnologySolar
Capacity250.0 MW
StateTexas
CountyLamar
Point of interconnectiontap both 345kV 1685 FarmersVl - 1695 Moses ckts
Requested (queue) date2020-01-13
Proposed in-service date
Operational date2026-09-30
Withdrawn date
DeveloperSamson Solar Energy III LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.