San Juan Tap 230kv substation (GEN-2022-023)

San Juan Tap 230kv substation is a 175.0 MW battery interconnection project in Chavez, New Mexico with a current status of withdrawn. It is proposed to connect at San Juan Tap 230kv substation.

175.0 MWCapacity
WithdrawnStatus
NMMarket
BatteryTechnology

Project facts

Canonical nameSan Juan Tap 230kv substation
Queue IDGEN-2022-023
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologyBattery
Capacity175.0 MW
StateNew Mexico
CountyChavez
Point of interconnectionSan Juan Tap 230kv substation
Requested (queue) date2022-06-08
Proposed in-service date2025-12-31
Operational date
Withdrawn date2023-11-06
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.