Sand Luis West (68673_SLW_S)

Sand Luis West is a 31.3 MW battery interconnection project in Fresno, California with a current status of active.

31.3 MWCapacity
ActiveStatus
CISOMarket
BatteryTechnology

Project facts

Canonical nameSand Luis West
Queue ID68673_SLW_S
Statusactive
Source status(T) Regulatory approvals received. Not under construction
MarketCISO
TechnologyBattery
Capacity31.3 MW
StateCalifornia
CountyFresno
Point of interconnection—
Requested (queue) date—
Proposed in-service date2028-11-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerOrigis Energy USA, Inc

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata