Sandwich 916 - EMA ASO (1285)

Sandwich 916 - EMA ASO is a 4.6 MW solar+battery interconnection project in Barnstable, Massachusetts with a current status of withdrawn. It is proposed to connect at Eversource Sandwich 916.

4.6 MWCapacity
WithdrawnStatus
SEMAMarket
Solar+BatteryTechnology

Project facts

Canonical nameSandwich 916 - EMA ASO
Queue ID1285
Statuswithdrawn
Source statusW
MarketSEMA
TechnologySolar+Battery
Capacity4.6 MW
StateMassachusetts
CountyBarnstable
Point of interconnectionEversource Sandwich 916
Requested (queue) date2022-06-08
Proposed in-service date2023-11-30
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata