SC Queue Project 229 — Battery in Berkeley, South Carolina

SC Queue Project 229 — Battery in Berkeley, South Carolina is a 150.0 MW battery interconnection project in Berkeley, South Carolina with a current status of withdrawn. It is proposed to connect at JAMESTOWN STATION (BERKELEY CO-OP DELIVERY POINT).

150.0 MWCapacity
WithdrawnStatus
SCMarket
BatteryTechnology

Project facts

Canonical nameSC Queue Project 229 — Battery in Berkeley, South Carolina
Queue ID229
Statuswithdrawn
Source statusWithdrawn
MarketSC
TechnologyBattery
Capacity150.0 MW
StateSouth Carolina
CountyBerkeley
Point of interconnectionJAMESTOWN STATION (BERKELEY CO-OP DELIVERY POINT)
Requested (queue) date2023-06-01
Proposed in-service date2028-06-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerSouth Carolina Public Service Authority (Santee Cooper)

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: santee-cooper-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.