Berkeley County, South Carolina — Interconnection Projects

The interXdata warehouse tracks 53 interconnection projects in Berkeley, South Carolina, representing 10,897 MW of requested capacity.

53Total projects
8Active
26Operational
19Withdrawn
10,897 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas204,957 MW
Other153,371 MW
Battery71,443 MW
Solar9730 MW
Solar+Battery2396 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Southeast Queue Project 20200910001 — Gas in Berkeley, South Carolina20200910001Gas870.0 MWwithdrawnBerkeley, South Carolina
Southeast Queue Project 20200910002 — Gas in Berkeley, South Carolina20200910002Gas720.0 MWwithdrawnBerkeley, South Carolina
Williams3298_ST1Other659.7 MWoperationalBerkeley, South Carolina
Cross130_3Other652.0 MWoperationalBerkeley, South Carolina
Cross130_4Other652.0 MWoperationalBerkeley, South Carolina
SC Queue Project 17 — Gas in Berkeley, South Carolina17Gas620.0 MWoperationalBerkeley, South Carolina
SC Queue Project 24 — Gas in Berkeley, South Carolina24Gas600.0 MWoperationalBerkeley, South Carolina
SC Queue Project 23 — Gas in Berkeley, South Carolina23Gas600.0 MWoperationalBerkeley, South Carolina
Cross130_1Other591.4 MWoperationalBerkeley, South Carolina
Cross130_2Other556.1 MWoperationalBerkeley, South Carolina
SC Queue Project 16 — Gas in Berkeley, South Carolina16Gas540.0 MWoperationalBerkeley, South Carolina
SC Queue Project 5 — Gas in Berkeley, South Carolina5Gas306.0 MWoperationalBerkeley, South Carolina
Southeast Queue Project GenRep1 — Battery in Berkeley, South CarolinaGenRep1Battery300.0 MWactiveBerkeley, South Carolina
Pinopolis BESS70020_1Battery300.0 MWactiveBerkeley, South Carolina
SC Queue Project 308 — Battery in Berkeley, South Carolina308Battery250.0 MWactiveBerkeley, South Carolina
SC Queue Project 321 — Solar in Berkeley, South Carolina321Solar199.0 MWactiveBerkeley, South Carolina
Southeast Queue Project 20230829013 — Battery in Berkeley, South Carolina20230829013Battery199.0 MWactiveBerkeley, South Carolina
SC Queue Project 205 — Solar+Battery in Berkeley, South Carolina205Solar+Battery198.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 206 — Solar+Battery in Berkeley, South Carolina206Solar+Battery198.0 MWactiveBerkeley, South Carolina
Southeast Queue Project 20230829014 — Battery in Berkeley, South Carolina20230829014Battery169.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 229 — Battery in Berkeley, South Carolina229Battery150.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 1 — Gas in Berkeley, South Carolina1Gas128.0 MWoperationalBerkeley, South Carolina
SC Queue Project 126 — Solar in Berkeley, South Carolina126Solar100.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 125 — Solar in Berkeley, South Carolina125Solar100.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 2 — Gas in Berkeley, South Carolina2Gas92.0 MWoperationalBerkeley, South Carolina
SC Queue Project 262 — Solar in Berkeley, South Carolina262Solar75.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 56 — Solar in Berkeley, South Carolina56Solar75.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 228 — Battery in Berkeley, South Carolina228Battery74.9 MWwithdrawnBerkeley, South Carolina
Southeast Queue Project 20211118005 — Gas in Berkeley, South Carolina20211118005Gas65.4 MWactiveBerkeley, South Carolina
Bushy Park Combustion Turbine Facility66600_CT1Gas65.4 MWoperationalBerkeley, South Carolina
Southeast Queue Project 80 — Solar in Berkeley, South Carolina80Solar65.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 80 — Solar in Berkeley, South Carolina80Solar60.0 MWwithdrawnBerkeley, South Carolina
SC Queue Project 342 — Gas in Berkeley, South Carolina342Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 338 — Gas in Berkeley, South Carolina338Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 340 — Gas in Berkeley, South Carolina340Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 341 — Gas in Berkeley, South Carolina341Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 339 — Gas in Berkeley, South Carolina339Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 337 — Gas in Berkeley, South Carolina337Gas55.6 MWwithdrawnBerkeley, South Carolina
SC Queue Project 159 — Solar in Berkeley, South Carolina159Solar50.0 MWwithdrawnBerkeley, South Carolina
Jefferies3319_H2Other36.9 MWoperationalBerkeley, South Carolina
Jefferies3319_H4Other36.9 MWoperationalBerkeley, South Carolina
Jefferies3319_H1Other30.6 MWoperationalBerkeley, South Carolina
Jefferies3319_H3Other30.6 MWoperationalBerkeley, South Carolina
Southeast Queue Project 35 — Other in Berkeley, South Carolina35Other28.5 MWoperationalBerkeley, South Carolina
St Stephen6789_2Other28.0 MWoperationalBerkeley, South Carolina
St Stephen6789_1Other28.0 MWoperationalBerkeley, South Carolina
St Stephen6789_3Other28.0 MWoperationalBerkeley, South Carolina
Southeast Queue Project 20211118001 — Gas in Berkeley, South Carolina20211118001Gas13.4 MWactiveBerkeley, South Carolina
Jefferies3319_H6Other10.2 MWoperationalBerkeley, South Carolina
Omtanke Solar63756_DGSC1Solar6.0 MWoperationalBerkeley, South Carolina
Spillway3321_1Other2.0 MWoperationalBerkeley, South Carolina
Berkeley County Landfill57945_B1Gas1.6 MWoperationalBerkeley, South Carolina
Berkeley County Landfill57945_B2Gas1.6 MWoperationalBerkeley, South Carolina

Top developers

Developer (canonical)ProjectsCapacity
SCPSA72,886 MW
DESC - Generation279 MW
Santee Cooper1300 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; santee-cooper-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.