Schahfer CCGTs is a 2,739.8 MW gas interconnection project in Jasper, Indiana with a current status of active. It is proposed to connect at Schahfer Gen Sta.
2,739.8 MWCapacity
ActiveStatus
MISOMarket
GasTechnology
Project facts
| Canonical name | Schahfer CCGTs |
|---|---|
| Queue ID | E0042 |
| Status | active |
| Source status | active |
| Market | MISO |
| Technology | Gas |
| Capacity | 2,739.8 MW |
| State | Indiana |
| County | Jasper |
| Point of interconnection | Schahfer Gen Sta |
| Requested (queue) date | 2025-08-06 |
| Proposed in-service date | 2028-08-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | NIPSCO |
| Utility / transmission owner | NIPSCO |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.