SCHNEIDER COMBINED CYCLE (30INR0054)

SCHNEIDER COMBINED CYCLE is a 880.0 MW gas interconnection project in Caldwell, Texas with a current status of operational. It is proposed to connect at Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs .

880.0 MWCapacity
OperationalStatus
CaldwellMarket
GasTechnology

Project facts

Canonical nameSCHNEIDER COMBINED CYCLE
Queue ID30INR0054
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketCaldwell
TechnologyGas
Capacity880.0 MW
StateTexas
CountyCaldwell
Point of interconnectionDouble Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs
Requested (queue) date2025-07-29
Proposed in-service date
Operational date2030-12-15
Withdrawn date
DeveloperLCRA
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.