SERENITY SOLAR is a 40.5 MW solar interconnection project in Fresno, California with a current status of withdrawn. It is proposed to connect at Coalinga #1 - San Miguel 70 kV line.

40.5 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameSERENITY SOLAR
Queue ID1247
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar
Capacity40.5 MW
StateCalifornia
CountyFresno
Point of interconnectionCoalinga #1 - San Miguel 70 kV line
Requested (queue) date2016-05-02
Proposed in-service date
Operational date
Withdrawn date2016-07-06
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.