Sheffield Solar (Solar Star 1) (15INR0041)

Sheffield Solar (Solar Star 1) is a 51.0 MW solar interconnection project with a current status of withdrawn. It is proposed to connect at Cactus (6579).

51.0 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameSheffield Solar (Solar Star 1)
Queue ID15INR0041
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity51.0 MW
State
County
Point of interconnectionCactus (6579)
Requested (queue) date2013-07-24
Proposed in-service date2015-09-01
Operational date
Withdrawn date
DeveloperSolar City
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata