Sherco BESS (70097_SWB)

Sherco BESS is a 300.0 MW battery interconnection project in Sherburne, Minnesota with a current status of active.

300.0 MWCapacity
ActiveStatus
MISOMarket
BatteryTechnology

Project facts

Canonical nameSherco BESS
Queue ID70097_SWB
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketMISO
TechnologyBattery
Capacity300.0 MW
StateMinnesota
CountySherburne
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-11-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerNORTHERN STATES POWER COMPANY

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata