Sideoats Solar 3 (30INR0125)

Sideoats Solar 3 is a 167.6 MW solar interconnection project in Throckmorton, Texas with a current status of active. It is proposed to connect at DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kV.

167.6 MWCapacity
ActiveStatus
ThrockmortonMarket
SolarTechnology

Project facts

Canonical nameSideoats Solar 3
Queue ID30INR0125
Statusactive
Source statusSS Started, FIS Started, No IA
MarketThrockmorton
TechnologySolar
Capacity167.6 MW
StateTexas
CountyThrockmorton
Point of interconnectionDUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kV
Requested (queue) date2026-09-18
Proposed in-service date2031-03-31
Operational date—
Withdrawn date—
DeveloperBush Knob Solar, LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-30new_project—activehigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-10-30
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.