Signal Hill BESS I (26INR0544)

Signal Hill BESS I is a 122.8 MW other interconnection project in Wichita, Texas with a current status of operational. It is proposed to connect at 138kV Wichita Falls Cogen (Bus #1498).

122.8 MWCapacity
OperationalStatus
WichitaMarket
OtherTechnology

Project facts

Canonical nameSignal Hill BESS I
Queue ID26INR0544
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketWichita
TechnologyOther
Capacity122.8 MW
StateTexas
CountyWichita
Point of interconnection138kV Wichita Falls Cogen (Bus #1498)
Requested (queue) date2024-09-04
Proposed in-service date—
Operational date2030-07-31
Withdrawn date—
DeveloperSignal Hill Generating LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31operational_date2029-12-312030-07-31medium
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.