Simple Cycle (439)

Simple Cycle is a 478.0 MW gas interconnection project in Essex, Massachusetts with a current status of withdrawn. It is proposed to connect at GRID Ward Hill – Tewksbury 345 kV line, approximately 1.8 miles from the Ward Hill.

478.0 MWCapacity
WithdrawnStatus
CMAMarket
GasTechnology

Project facts

Canonical nameSimple Cycle
Queue ID439
Statuswithdrawn
Source statusW
MarketCMA
TechnologyGas
Capacity478.0 MW
StateMassachusetts
CountyEssex
Point of interconnectionGRID Ward Hill – Tewksbury 345 kV line, approximately 1.8 miles from the Ward Hill
Requested (queue) date2014-02-24
Proposed in-service date2018-05-01
Operational date
Withdrawn date2015-02-12
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.