Singing Grass Wind (68982_SGG01)

Singing Grass Wind is a 603.0 MW wind interconnection project in Kit Carson, Colorado with a current status of active.

603.0 MWCapacity
ActiveStatus
PSCOMarket
WindTechnology

Project facts

Canonical nameSinging Grass Wind
Queue ID68982_SGG01
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketPSCO
TechnologyWind
Capacity603.0 MW
StateColorado
CountyKit Carson
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-09-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerPublic Service Company Of Colorado

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-02proposed_online_date2026-08-012027-09-01medium
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.