Sisters Solar - Phase 2 (27INR0570)
Sisters Solar - Phase 2 is a 201.5 MW solar interconnection project in Ector, Texas with a current status of active. It is proposed to connect at 10009 McGee 345 kV.
201.5 MWCapacity
ActiveStatus
EctorMarket
SolarTechnology
Project facts
| Canonical name | Sisters Solar - Phase 2 |
|---|---|
| Queue ID | 27INR0570 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Ector |
| Technology | Solar |
| Capacity | 201.5 MW |
| State | Texas |
| County | Ector |
| Point of interconnection | 10009 McGee 345 kV |
| Requested (queue) date | 2026-07-22 |
| Proposed in-service date | 2028-09-23 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Oberon Solar III, LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-09-30 | proposed_online_date | 2028-05-31 | 2028-09-23 | medium |
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.