Slaton BESS (25INR0689)
Slaton BESS is a 10.0 MW battery interconnection project with a current status of active. It is proposed to connect at Station Name: Slaton Substation • Station Code: LPLSL • BUS #: 59152 • Transmission Level Voltage: 115 kV • Load/Load Transformer: SLT1 • Node (associated w/ load/load XFMR in NMMS): SL15.
Project facts
| Canonical name | Slaton BESS |
|---|---|
| Queue ID | 25INR0689 |
| Status | active |
| Source status | active |
| Market | ERCOT |
| Technology | Battery |
| Capacity | 10.0 MW |
| State | — |
| County | — |
| Point of interconnection | Station Name: Slaton Substation • Station Code: LPLSL • BUS #: 59152 • Transmission Level Voltage: 115 kV • Load/Load Transformer: SLT1 • Node (associated w/ load/load XFMR in NMMS): SL15 |
| Requested (queue) date | 2025-06-12 |
| Proposed in-service date | 2025-08-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Prairie Dog BESS, LLC |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.