Solar (1033)

Solar is a 6.0 MW solar interconnection project in Ellington, Connecticut with a current status of withdrawn. It is proposed to connect at Eversource Scitico #27H9.

6.0 MWCapacity
WithdrawnStatus
CTMarket
SolarTechnology

Project facts

Canonical nameSolar
Queue ID1033
Statuswithdrawn
Source statusW
MarketCT
TechnologySolar
Capacity6.0 MW
StateConnecticut
CountyEllington
Point of interconnectionEversource Scitico #27H9
Requested (queue) date2020-06-24
Proposed in-service date2024-09-01
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata