Southeast Queue Project 20240829001 — Solar+Battery in Richland, South Carolina
Southeast Queue Project 20240829001 — Solar+Battery in Richland, South Carolina is a 250.0 MW solar+battery interconnection project in Richland, South Carolina with a current status of active. It is proposed to connect at Wateree - Hopkins 230 kV #2.
Project facts
| Canonical name | Southeast Queue Project 20240829001 — Solar+Battery in Richland, South Carolina |
|---|---|
| Queue ID | 20240829001 |
| Status | active |
| Source status | active |
| Market | Southeast |
| Technology | Solar+Battery |
| Capacity | 250.0 MW |
| State | South Carolina |
| County | Richland |
| Point of interconnection | Wateree - Hopkins 230 kV #2 |
| Requested (queue) date | — |
| Proposed in-service date | 2028-12-29 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Dominion |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata