Southeast Queue Project 628 — Gas in Todd, Kentucky

Southeast Queue Project 628 — Gas in Todd, Kentucky is a 1,600.0 MW gas interconnection project in Todd, Kentucky with a current status of active. It is proposed to connect at PARADISE - MONTGOMERY 500 KV.

1,600.0 MWCapacity
ActiveStatus
SoutheastMarket
GasTechnology

Project facts

Canonical nameSoutheast Queue Project 628 — Gas in Todd, Kentucky
Queue ID628
Statusactive
Source statusactive
MarketSoutheast
TechnologyGas
Capacity1,600.0 MW
StateKentucky
CountyTodd
Point of interconnectionPARADISE - MONTGOMERY 500 KV
Requested (queue) date2024-06-12
Proposed in-service date2030-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerTennessee Valley Authority

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata