Spindletop Solar (27INR0313)

Spindletop Solar is a 286.4 MW solar interconnection project in Nacogdoches, Texas with a current status of operational. It is proposed to connect at Tap Stryker [3109] - Lufkin [3117] 345 kV line.

286.4 MWCapacity
OperationalStatus
NacogdochesMarket
SolarTechnology

Project facts

Canonical nameSpindletop Solar
Queue ID27INR0313
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketNacogdoches
TechnologySolar
Capacity286.4 MW
StateTexas
CountyNacogdoches
Point of interconnectionTap Stryker [3109] - Lufkin [3117] 345 kV line
Requested (queue) date2024-07-30
Proposed in-service date
Operational date2027-12-29
Withdrawn date
DeveloperBanita Creek Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata