Springdale 138kV (V1-013)

Springdale 138kV is a 580.0 MW other interconnection project in Allegheny, Pennsylvania with a current status of withdrawn.

580.0 MWCapacity
WithdrawnStatus
—Market
OtherTechnology

Project facts

Canonical nameSpringdale 138kV
Queue IDV1-013
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyOther
Capacity580.0 MW
StatePennsylvania
CountyAllegheny
Point of interconnection—
Requested (queue) date2009-02-27
Proposed in-service date2012-01-01
Operational date—
Withdrawn date2009-09-11
Developer—
Utility / transmission ownerAPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.