SR Bartow (GI-204)

SR Bartow is a 200.0 MW solar interconnection project in Jefferson County, Georgia with a current status of active. It is proposed to connect at Sandersville #1 - Wadley 115 kV via Pervis Road.

200.0 MWCapacity
ActiveStatus
GAMarket
SolarTechnology

Project facts

Canonical nameSR Bartow
Queue IDGI-204
Statusactive
Source statusExecuted IA - NTP
MarketGA
TechnologySolar
Capacity200.0 MW
StateGeorgia
CountyJefferson County
Point of interconnectionSandersville #1 - Wadley 115 kV via Pervis Road
Requested (queue) date2024-12-18
Proposed in-service date2029-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: gtc-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.