SR Millen (GI-207)

SR Millen is a 65.0 MW solar interconnection project in Jenkins County, Georgia with a current status of suspended. It is proposed to connect at Millen Primary - Waynesboro 115 kV line.

65.0 MWCapacity
SuspendedStatus
GAMarket
SolarTechnology

Project facts

Canonical nameSR Millen
Queue IDGI-207
Statussuspended
Source statusOn Hold
MarketGA
TechnologySolar
Capacity65.0 MW
StateGeorgia
CountyJenkins County
Point of interconnectionMillen Primary - Waynesboro 115 kV line
Requested (queue) date2025-01-08
Proposed in-service date2029-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectsuspendedhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: gtc-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata